Innovation trials tackle challenges on peat-affected roads in Cambridgeshire

Guest piece from India Harding, PhD student, FIBE2 CDT, University of Cambridge

In October, Dr Mashael Kamran (Research Associate, DARe) and India Harding (PhD student, FIBE2 CDT, University of Cambridge) attended the media day of the soils affected roads Innovation Trials on Upwell Road (B1099) in March, Cambridgeshire, to see a range of ground stabilisation techniques being trialled on one of the Fens’ most challenging road subgrades: peat.

India Harding and Mashael Kamran smile at the camera whilst onsite at the soils affected roads Innovation Trials in Cambridgeshire
India Harding and Dr Mashael Kamran

Around 40% of Cambridgeshire’s road network – approximately 1,118 miles (1,800 km) – are constructed on peat soils, and the county estimates that repairing roads on peatland can cost up to five times more than equivalent works on other ground conditions (Dunlop, 2026). Cambridgeshire County Council, one of DARe’s Project Partners, has previously stated it faces an £800 million road‑maintenance backlog due to “decades of underfunding”, with £500 million required just to fix roads built on peatland (Dunlop, 2026). The project, led by Cambridgeshire County Council, with Cambridgeshire Highways overseeing delivery, the project aims to investigate innovative approaches to stabilising roads built on peat. Peat presents significant engineering challenges because its high moisture content and compressibility make it susceptible to settlement, swelling, and shrinkage as environmental conditions change. Climate change is expected to exacerbate these challenges through increased drought and flooding risks, potentially accelerating peat shrinkage and ground subsidence (EA, 2026). These behaviours can contribute to uneven road surfaces, subsidence, and extensive cracking.

The challenges were evident on the drive to the site, where we observed pronounced dips near trees and road edges, uneven surfaces, and wide longitudinal cracks. One memorable fact from the visit illustrated just how unusual peat is as an engineering material: a pint glass of peat contains approximately the same volume of solids as a pint glass of milk! This exceptionally high proportion of water helps explain why stabilising peat requires a different approach from conventional road subgrades.

Paul Bristow, Mayor of Cambridgeshire and Peterborough (left), helps roll out a geogrid

The trials compare seven different stabilisation methods, each designed to address the challenges of working with peat in a different way.

  • Section 1 – Deep soil mixing: A cementitious binder is mixed into the ground to form buttresses, helping restrain lateral movement and influence deeper water movement.
  • Sections 2, 4, and 7 – Stabilisation grids: Different grid systems are installed at approximately 150 mm depth and filled with granular or lightweight granular materials. Section 7 is particularly interesting because it retains the existing road base, whereas most other approaches involve planing the road to approximately 400 mm before construction.
  • Section 3 – Polymer resin injection: Resin is injected into the road base through small holes at approximately 1m intervals to fill voids and stabilise the underlying material. This approach is minimally disruptive to the road surface.
  • Section 5 – Reinforcement grids: A metal reinforcement grid, comparable in appearance to strengthened chicken wire, is combined with asphalt reinforcement and a lightweight granular layer to improve stability.
  • Section 6 – Strataweb: A three-dimensional soil-stabilisation system is installed as a 150 mm layer, with the embankments retained using topsoil and soil-retention matting. It was particularly good to see the local mayor getting involved in rolling out the system!
Alex Beckett, Cambridgeshire County Council, demonstrates the peat/milk comparison

Once construction is complete, the trial sections will undergo three years of monitoring using in-situ and remote sensors to track changes in moisture and ground movement. The findings will help determine which techniques perform most effectively under real-world conditions, with the longer-term ambition of applying successful approaches to other roads affected by peat across the region.

The visit offered a valuable opportunity to see how different engineering solutions are being applied to a complex ground engineering challenge, and how long-term monitoring can inform decisions about more resilient road infrastructure. Data on the cost and carbon of the treatments are being captured, which will help enable comparisons of the different maintenance regimes.

And, with the sun shining on a crisp autumn day in the Fens, it was a great opportunity to get out on site, see the works taking shape, and learn from the teams delivering the trials.

References

Dunlop, A. (2026) ‘Seven ways to repair peat-soil roads being tried’, BBC News. 11 October. Available at: Seven repairs to peat-soil roads tested on Upwell Road at March – BBC News (Accessed: 11 October 2026)

Environment Agency (2026) Fens 2100+: Summary baseline report. Available at: https://www.gov.uk/government/publications/fens-2100/fens-2100-summary-baseline-report (Accessed: 11 October 2026)

DARe
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.